Question 36

A companys data center is running out of compute resources (CPU and Memory). As a result, the
administration team decided to optimize the CPU and memory value assigned to each virtual
machine to save some compute resources.
How can the administrators use vRealize Operations Manager to achieve this goal?

  • A. Under Workload Optimization, click optimize now, and run the recommended actions.
  • B. Under Rightsizing, select the oversized virtual machines, and click resize.
  • C. Under Recommended Actions, check the alerts, and apply the suggested fix.
  • D. Under Reclaim, select the snapshots shown, and click delete.
Answer:

A


Explanation:
Reference:
https://docs.vmware.com/en/VMware-vRealize-Operations-Cloud/services/config-guide/GUID-3CB9B8AB-03CA-4755-AC94-929B1A6B6C5D.html

User Votes:
A
50%
B 1 votes
50%
C
50%
D
50%
Discussions
0 / 1000
ankitmalhotra
2 weeks, 5 days ago

B, because they want to reclaim the resources, best to do it for oversized vms