psm-ii question 183 discussion

View all Professional Scrum Master level II (PSM II) here
back to scrum forum

Question 183

Who should manage the tasks of Development Team during the Sprint?

  • A. The Project Manager.
  • B. The Product Owner.
  • C. The Scrum Master.
  • D. The Development Team.
  • E. All of the above.
Answer:

D


Explanation:
The Development Team is responsible for managing and tracking the progress of their work during a Sprint

User Votes:
A
50%
B
50%
C 1 votes
50%
D 1 votes
50%
E
50%
Discussions
0 / 1000
JUJUSHINE
2 months ago

answer is c