Question 181

How often should Development Team membership change?

  • A. Frequently in order to share knowledge.
  • B. As needed, while taking into account a short term reduction in productivity.
  • C. Never, as it conflicts with the Scrum process.
  • D. As needed, as long as it doesn’t impact productivity.
Answer:

B


Explanation:
It is not mandatory that the same team stay together, although it must be understood that any changes to the team will
impact how they work together.