What is we do in ACT - From PDCA cycle

  • B. Take actions to continually improve process performance Most Votes
  • C. Take actions to continually monitor process performance
  • D. Take actions to continually improve people performance
Answer:

B


User Votes:
B 64 votes
50%
C 11 votes
50%
D 6 votes
50%
Discussions
0 / 1000
ashok
1 year, 1 month ago

Take actions to continually improve process performance

ashok
1 year, 1 month ago

Take actions to continually improve process performance

robdavies66
8 months, 1 week ago

Take actions to continually improve process performance

robdavies66
8 months ago

Take actions to continually improve process performance

ASRARMA
7 months, 1 week ago

B. Take actions to continually improve process performance

Mans
7 months ago

Take actions to continually improve process performance

Priyachoudhari
6 months, 3 weeks ago

Continuly improve process performance

grosso62
2 months, 1 week ago

B. Take actions to continually improve process performance

grosso62
2 months ago

B. Take actions to continually improve process performance

syma1970
2 weeks, 6 days ago

The "Act" phase is where you standardize successful changes, or take corrective actions if the results were not as expected.