Question 34

Which time elements are part of a routing operation? Note: There are 3 correct answers to this
question.

  • A. Queue time
  • B. Float before production
  • C. Pick/pack time
  • D. Wait time
  • E. Move time
Answer:

A, C, D


User Votes:
A
50%
B
50%
C
50%
D
50%
E
50%
Discussions
0 / 1000
neha.rai.2803
1 year, 2 months ago

Why not option E instead of C