c-ts410-2020 question 98 discussion

View all SAP Certified Application Associate - Business Process Integration with SAP S/4HANA 2020 Exam here
back to sap forum

Question 98

What MRP control parameter defines the scope of a planning run when the system only takes into
account changes that are within the planning? Please choose the correct answer.

  • A. Planning mode
  • B. Processing key - NETCH Most Votes
  • C. Procurement type
  • D. Processing key - NEUPL
Answer:

B


User Votes:
A 15 votes
50%
B 63 votes
50%
C 7 votes
50%
D 10 votes
50%
Discussions
0 / 1000
aphiwe.andisa.radebe
1 year, 6 months ago

Processing key-NETCH

aphiwe.andisa.radebe
1 year, 6 months ago

Processing key - NETCH

molka
1 year, 5 months ago

B. Processing key - NETCH

ngocto170703
1 year, 1 month ago

B. Processing key - NETCH

jonathan
1 year, 1 month ago

a a a a a a a

vytnt1704
1 year, 1 month ago

B - Processing key - NETCH

vytnt1704
1 year, 1 month ago

B - Processing key - NETCH

vytnt1704
1 year, 1 month ago

Thanks for submitting , your comment will be approved soon by our moderators

Fatma
11 months ago

Processing key-NETCH

84mqdoan
9 months, 1 week ago

Processing key - NETCH

Lamrinizakaria10
8 months, 3 weeks ago

Processing key - NETCH

souleypower
8 months, 2 weeks ago

B. Processing key - NETCH

reuter.jessi
6 months, 2 weeks ago

Processing key - NETCH

sharon.adedokun
5 months, 3 weeks ago

Processing key - NETCH

Umar
4 months ago

Procurement type

Pacnt1
3 months ago

Processing key - NETCH