What MRP control parameter defines the scope of a planning run when the system only takes into account changes that are within the planning? Please choose the correct answer.
A.
Planning mode
B.
Processing key - NETCH
Most Votes
C.
Procurement type
D.
Processing key - NEUPL
Answer:
B
User Votes:
A 16 votes
50%
B 65 votes
50%
C 7 votes
50%
D 10 votes
50%
Discussions
0/ 1000
aphiwe.andisa.radebe
1 year, 7 months ago
Processing key-NETCH
aphiwe.andisa.radebe
1 year, 7 months ago
Processing key - NETCH
molka
1 year, 6 months ago
B. Processing key - NETCH
ngocto170703
1 year, 3 months ago
B. Processing key - NETCH
jonathan
1 year, 3 months ago
a a a a a a a
vytnt1704
1 year, 2 months ago
B - Processing key - NETCH
vytnt1704
1 year, 2 months ago
B - Processing key - NETCH
vytnt1704
1 year, 2 months ago
Thanks for submitting , your comment will be approved soon by our moderators
Fatma
1 year ago
Processing key-NETCH
84mqdoan
10 months, 2 weeks ago
Processing key - NETCH
Lamrinizakaria10
9 months, 3 weeks ago
Processing key - NETCH
souleypower
9 months, 3 weeks ago
B. Processing key - NETCH
reuter.jessi
7 months, 3 weeks ago
Processing key - NETCH
sharon.adedokun
7 months ago
Processing key - NETCH
Umar
5 months ago
Procurement type
Pacnt1
4 months ago
Processing key - NETCH
Want to join our community?
Please log in or signup in order to use this feature
Processing key-NETCH
Processing key - NETCH
B. Processing key - NETCH
B. Processing key - NETCH
a a a a a a a
B - Processing key - NETCH
B - Processing key - NETCH
Thanks for submitting , your comment will be approved soon by our moderators
Processing key-NETCH
Processing key - NETCH
Processing key - NETCH
B. Processing key - NETCH
Processing key - NETCH
Processing key - NETCH
Procurement type
Processing key - NETCH