Question 98

What MRP control parameter defines the scope of a planning run when the system only takes into
account changes that are within the planning? Please choose the correct answer.

  • A. Planning mode
  • B. Processing key - NETCH Most Votes
  • C. Procurement type
  • D. Processing key - NEUPL
Answer:

B


User Votes:
A 15 votes
50%
B 63 votes
50%
C 6 votes
50%
D 9 votes
50%
Discussions
0 / 1000
aphiwe.andisa.radebe
1 year, 5 months ago

Processing key-NETCH

aphiwe.andisa.radebe
1 year, 5 months ago

Processing key - NETCH

molka
1 year, 4 months ago

B. Processing key - NETCH

ngocto170703
1 year ago

B. Processing key - NETCH

jonathan
1 year ago

a a a a a a a

vytnt1704
1 year ago

B - Processing key - NETCH

vytnt1704
1 year ago

B - Processing key - NETCH

vytnt1704
1 year ago

Thanks for submitting , your comment will be approved soon by our moderators

Fatma
9 months, 3 weeks ago

Processing key-NETCH

84mqdoan
8 months ago

Processing key - NETCH

Lamrinizakaria10
7 months, 2 weeks ago

Processing key - NETCH

souleypower
7 months, 2 weeks ago

B. Processing key - NETCH

reuter.jessi
5 months, 2 weeks ago

Processing key - NETCH

sharon.adedokun
4 months, 3 weeks ago

Processing key - NETCH

Umar
2 months, 3 weeks ago

Procurement type