What MRP control parameter defines the scope of a planning run when the system only takes into account changes that are within the planning? Please choose the correct answer.
A.
Planning mode
B.
Processing key - NETCH
Most Votes
C.
Procurement type
D.
Processing key - NEUPL
Answer:
B
User Votes:
A 4 votes
50%
B 13 votes
50%
C 2 votes
50%
D 1 votes
50%
Discussions
0/ 1000
navenk
1 year, 4 months ago
B. Processing key - NETCH
crossfit202
6 months, 1 week ago
Processing key - NETCH
renzymathew
5 months, 1 week ago
Procurement type
Want to join our community?
Please log in or signup in order to use this feature
B. Processing key - NETCH
Processing key - NETCH
Procurement type