iso-iec-27001-lead-auditor question 97 discussion

View all ISO/IEC 27001 Lead Auditor Exam here
back to pecb forum

Question 97

Implement plan on a test basis - this comes under which section of PDCA

  • A. Plan
  • B. Do Most Votes
  • C. Act
  • D. Check
Answer:

B


User Votes:
A 18 votes
50%
B 51 votes
50%
C 14 votes
50%
D 5 votes
50%
Discussions
0 / 1000
Abansal
1 year, 5 months ago

The answer is "DO"

ashok
1 year, 2 months ago

Do Implement plan on a test basis

robdavies66
9 months, 2 weeks ago

The answer is B:Do

robdavies66
9 months, 1 week ago

B. Do B. Do

ASRARMA
8 months, 2 weeks ago

the answer is B. Do

Mans
8 months, 1 week ago

Check implement plan on a test basis

Priyachoudhari
8 months ago

Do under pdca

grosso62
3 months, 3 weeks ago

This comes under section of PDCA Do

syma1970
1 month, 4 weeks ago

When you "implement a plan on a test basis," you are performing the "Do" portion of the PDCA

mettie.vandenberg
3 weeks, 2 days ago

implement is DO