A client has a primary data center that is located in a coastal area where the forecast is calling for a
Category 5 hurricane to make landfall in three days. The clients data is protected using NetApp SVM
SnapMirror replication technology with identity-preserve that is enabled. The data is mirrored to a
destination cluster outside of the affected are
a. The client has scheduled a controlled maintenance window for tomorrow to ensure that
dependable operations are maintained.
Which three steps must be taken to accomplish this task? (Choose three.)

  • A. You must break the SnapMirror relationship on each individual volume between the source and the destination clusters.
  • B. You must configure the destination SVM volumes for data access.
  • C. You must reboot each server in your infrastructure so that they can access the data from the destination volumes.
  • D. You must break the SnapMirror relationship between the source and the destination SVMs.
  • E. You must stop the source SVM before activating the destination SVM.
Answer:

B,D,E


User Votes:
A
50%
B
50%
C
50%
D
50%
E
50%
Discussions
0 / 1000
Guss
1 year, 3 months ago

yes that's good