A customer currently has a CS1000H and wants to upgrade to a CS3000.
What must be considered before upgrading?

  • A. This upgrade is disruptive and needs planned downtime.
  • B. A capacity upgrade to a fully populated array has to be performed first.
  • C. Timeless storage support is not offered for CS1000H entry-level systems.
  • D. A controller upgrade to a CS1000F has to be performed first.
Answer:

B

User Votes:
A 2 votes
50%
B
50%
C
50%
D
50%
Discussions
0 / 1000
Selami
1 month ago

I think wrong because first plan