The operation that controls the work feeding the bottleneck and must operate at a rate equal to the
utput of the bottleneck so the time buffer queue is maintained is known as:
A. gateway operation
B. bottleneck operation
C. task operation
D. Control buffer operation
A
A facility, function, department, or resource whose capacity is equal to or less than the demand
placed upon it is known as:
B
The time needed to unload and load must be shorter than .
A
Operational splitting is practical when:
D
If the run time per piece on operation B is shorter than that on A, the first batch must be larger
enough to avoid idle time on operation A
B
Backward scheduling is used to determine when an order must be started.
A
When the last operation is on the routing is scheduled first and is scheduled for complete at the due
date, this is called:
D
What is used to calculate how long it will take to complete a task?
A
The length of time from when material enters a production facility until it exists, this is known as:
A
What must manage both the input of orders to the production process and the availability capacity to
control queue and work-in process?
B
Which of the following is NOT the manufacturing lead time?
D
The time normally required to produce an item in a typical lot quantity is known as:
D
Each active manufacturing order has a record in which file?
C
What consist of a series of operations required to make the item?
A
Which file contains a list of the single-level components and quantities needed to assemble a
parent?
B